How to allow enable the weekends as working period in gantt project?











up vote
5
down vote

favorite
1












My question is similar to this one: How can I enable a weekend as working period? (no answers).



I want to plan a wedding in gantt project, where all days are considered working days. How can I do that? I have fiddled with options, but didn't found anything about weekends.










share|improve this question




























    up vote
    5
    down vote

    favorite
    1












    My question is similar to this one: How can I enable a weekend as working period? (no answers).



    I want to plan a wedding in gantt project, where all days are considered working days. How can I do that? I have fiddled with options, but didn't found anything about weekends.










    share|improve this question


























      up vote
      5
      down vote

      favorite
      1









      up vote
      5
      down vote

      favorite
      1






      1





      My question is similar to this one: How can I enable a weekend as working period? (no answers).



      I want to plan a wedding in gantt project, where all days are considered working days. How can I do that? I have fiddled with options, but didn't found anything about weekends.










      share|improve this question















      My question is similar to this one: How can I enable a weekend as working period? (no answers).



      I want to plan a wedding in gantt project, where all days are considered working days. How can I do that? I have fiddled with options, but didn't found anything about weekends.







      project-management gantt






      share|improve this question















      share|improve this question













      share|improve this question




      share|improve this question








      edited May 31 '13 at 2:36









      Karan

      48.7k1486156




      48.7k1486156










      asked May 30 '13 at 16:05









      Benjamin Crouzier

      1,96392440




      1,96392440






















          7 Answers
          7






          active

          oldest

          votes

















          up vote
          6
          down vote













          You can go to Project->Proprietes->Calendar Project and there you can choose weekend's days






          share|improve this answer





















          • As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
            – Eric Hepperle - CodeSlayer2010
            Jul 22 '16 at 21:10


















          up vote
          4
          down vote













          "I figured it out. There seems to be no way of changing the weekends after a project is started, but there is an option when you start a new project. I just created a new project and imported the previous schedule."



          taken from: " http://blenderartists.org/forum/showthread.php?59865-GanttProject-Weekends "



          Hope this helps, it should be setup before your project






          share|improve this answer




























            up vote
            2
            down vote













            You can change working days (even in existing project) by changing settings of your Project Calendar and adding working hours for Saturday and Sunday.



            See: https://support.office.com/client/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c






            share|improve this answer





















            • External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
              – fixer1234
              Oct 10 '15 at 0:52










            • I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
              – Eric Hepperle - CodeSlayer2010
              Jul 22 '16 at 20:54


















            up vote
            0
            down vote













            I have planned many projects where tasks were permitted to be worked on over weekends. It is just a matter of setting the correct working time for the resources assigned to the task. If the resource(s) assigned are permitted to work on Saturday and Sunday then any tasks to which they are assigned will automatically be scheduled on those days.



            How you set the working time for resources differs depending on which version of Project you are using. It changed slightly from MS-P 2010 onwards.



            In both versions you go to the Resource Sheet, select the resource you want to modify and double-click on their calendar (right hand side of sheet). A common source of confusion is that the calendar is named the same as the Project's calendar, but when selected from the Resource Sheet is specific and personal to that user alone.



            Having opened the resource's calendar's Change Working Time dialog it now differs depending on verison. In 2010 onward you go to the Working Week tab and enter a new [default] entry, then select the "Details" button and ensure you have selected all days on which the user is working. Accept the changes and ensure the dates are correct for the period of time the resource is working the new hours. You can add as many rows describing non-standard hours as you want...



            On prior versions of MS-P, if I can remember correctly, you need to select Sat and Sun in the column headers of the calendar box and then click the radio button indicating Working Days or Non-Standard Working Days (in which case you need to manually enter the hours they work on the selected days).



            Typically I have normal working resources, set up the usual way, and then specific weekend-working resources who work weekend shifts to get stuff done, but do not work normal weekdays. So I create two (or more) different resources, one with weekday working and one with weekend working. When I assign a weekend-working-only resource to a task MS-P will only schedule it to be worked on over the weekend. But you could easily mix and match within a single resource...



            These kinds of changes can be done at any time during a project- If you suddenly realise you need to get something done over a weekend, just apply a resource to it that can work over the weekend and the task will be scheduled over a weekend. Changed your mind? Just allocate a different (non-weekend working) resource and the task will be scheduled for the working week (you'll have to recalcuate/levle the plan obviously, it won't just happen automatically)






            share|improve this answer



















            • 1




              It appears that the OP was not using MS Project, his question specifies GanttProject.
              – dav
              Jan 27 '14 at 17:37










            • Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
              – Marv Mills
              Jan 29 '14 at 13:10


















            up vote
            0
            down vote













            there is a solution. On Calender you can change the properties for the 24 hours calender. Then you enter the standard hour and select treat "sunday as standard" and treat "saturday as standard". You have to enter the working hours again but, each time you select it. Then I assigned to all ressources the 24hours calender and it worked fine for me.






            share|improve this answer




























              up vote
              0
              down vote













              Project > Properties > Duration > change number of days in a month to 31 instead of the default 20.






              share|improve this answer




























                up vote
                0
                down vote













                how to add an occasional weekend to be a working weekend?



                You can go to Project->Properties->Calendar
                go to One-off tab
                click on Add
                put in the target saturday or sunday

                Change the type from "holiday" to "working" day
                then
                Continue to charge forward in life with a smile






                share|improve this answer





















                  Your Answer








                  StackExchange.ready(function() {
                  var channelOptions = {
                  tags: "".split(" "),
                  id: "3"
                  };
                  initTagRenderer("".split(" "), "".split(" "), channelOptions);

                  StackExchange.using("externalEditor", function() {
                  // Have to fire editor after snippets, if snippets enabled
                  if (StackExchange.settings.snippets.snippetsEnabled) {
                  StackExchange.using("snippets", function() {
                  createEditor();
                  });
                  }
                  else {
                  createEditor();
                  }
                  });

                  function createEditor() {
                  StackExchange.prepareEditor({
                  heartbeatType: 'answer',
                  convertImagesToLinks: true,
                  noModals: true,
                  showLowRepImageUploadWarning: true,
                  reputationToPostImages: 10,
                  bindNavPrevention: true,
                  postfix: "",
                  imageUploader: {
                  brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
                  contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
                  allowUrls: true
                  },
                  onDemand: true,
                  discardSelector: ".discard-answer"
                  ,immediatelyShowMarkdownHelp:true
                  });


                  }
                  });














                  draft saved

                  draft discarded


















                  StackExchange.ready(
                  function () {
                  StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fsuperuser.com%2fquestions%2f601713%2fhow-to-allow-enable-the-weekends-as-working-period-in-gantt-project%23new-answer', 'question_page');
                  }
                  );

                  Post as a guest















                  Required, but never shown

























                  7 Answers
                  7






                  active

                  oldest

                  votes








                  7 Answers
                  7






                  active

                  oldest

                  votes









                  active

                  oldest

                  votes






                  active

                  oldest

                  votes








                  up vote
                  6
                  down vote













                  You can go to Project->Proprietes->Calendar Project and there you can choose weekend's days






                  share|improve this answer





















                  • As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
                    – Eric Hepperle - CodeSlayer2010
                    Jul 22 '16 at 21:10















                  up vote
                  6
                  down vote













                  You can go to Project->Proprietes->Calendar Project and there you can choose weekend's days






                  share|improve this answer





















                  • As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
                    – Eric Hepperle - CodeSlayer2010
                    Jul 22 '16 at 21:10













                  up vote
                  6
                  down vote










                  up vote
                  6
                  down vote









                  You can go to Project->Proprietes->Calendar Project and there you can choose weekend's days






                  share|improve this answer












                  You can go to Project->Proprietes->Calendar Project and there you can choose weekend's days







                  share|improve this answer












                  share|improve this answer



                  share|improve this answer










                  answered Mar 16 '15 at 10:58









                  Mitro

                  17729




                  17729












                  • As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
                    – Eric Hepperle - CodeSlayer2010
                    Jul 22 '16 at 21:10


















                  • As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
                    – Eric Hepperle - CodeSlayer2010
                    Jul 22 '16 at 21:10
















                  As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
                  – Eric Hepperle - CodeSlayer2010
                  Jul 22 '16 at 21:10




                  As of 2016 this answer is correct and works. Verified with Gantt Project 2.7.2.
                  – Eric Hepperle - CodeSlayer2010
                  Jul 22 '16 at 21:10












                  up vote
                  4
                  down vote













                  "I figured it out. There seems to be no way of changing the weekends after a project is started, but there is an option when you start a new project. I just created a new project and imported the previous schedule."



                  taken from: " http://blenderartists.org/forum/showthread.php?59865-GanttProject-Weekends "



                  Hope this helps, it should be setup before your project






                  share|improve this answer

























                    up vote
                    4
                    down vote













                    "I figured it out. There seems to be no way of changing the weekends after a project is started, but there is an option when you start a new project. I just created a new project and imported the previous schedule."



                    taken from: " http://blenderartists.org/forum/showthread.php?59865-GanttProject-Weekends "



                    Hope this helps, it should be setup before your project






                    share|improve this answer























                      up vote
                      4
                      down vote










                      up vote
                      4
                      down vote









                      "I figured it out. There seems to be no way of changing the weekends after a project is started, but there is an option when you start a new project. I just created a new project and imported the previous schedule."



                      taken from: " http://blenderartists.org/forum/showthread.php?59865-GanttProject-Weekends "



                      Hope this helps, it should be setup before your project






                      share|improve this answer












                      "I figured it out. There seems to be no way of changing the weekends after a project is started, but there is an option when you start a new project. I just created a new project and imported the previous schedule."



                      taken from: " http://blenderartists.org/forum/showthread.php?59865-GanttProject-Weekends "



                      Hope this helps, it should be setup before your project







                      share|improve this answer












                      share|improve this answer



                      share|improve this answer










                      answered May 30 '13 at 16:14









                      Will Webb

                      1675




                      1675






















                          up vote
                          2
                          down vote













                          You can change working days (even in existing project) by changing settings of your Project Calendar and adding working hours for Saturday and Sunday.



                          See: https://support.office.com/client/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c






                          share|improve this answer





















                          • External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
                            – fixer1234
                            Oct 10 '15 at 0:52










                          • I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
                            – Eric Hepperle - CodeSlayer2010
                            Jul 22 '16 at 20:54















                          up vote
                          2
                          down vote













                          You can change working days (even in existing project) by changing settings of your Project Calendar and adding working hours for Saturday and Sunday.



                          See: https://support.office.com/client/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c






                          share|improve this answer





















                          • External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
                            – fixer1234
                            Oct 10 '15 at 0:52










                          • I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
                            – Eric Hepperle - CodeSlayer2010
                            Jul 22 '16 at 20:54













                          up vote
                          2
                          down vote










                          up vote
                          2
                          down vote









                          You can change working days (even in existing project) by changing settings of your Project Calendar and adding working hours for Saturday and Sunday.



                          See: https://support.office.com/client/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c






                          share|improve this answer












                          You can change working days (even in existing project) by changing settings of your Project Calendar and adding working hours for Saturday and Sunday.



                          See: https://support.office.com/client/Change-working-days-for-the-project-calendar-323ff403-a676-428c-be11-6942bfb7210c







                          share|improve this answer












                          share|improve this answer



                          share|improve this answer










                          answered Dec 6 '14 at 20:41









                          Adam W

                          6129




                          6129












                          • External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
                            – fixer1234
                            Oct 10 '15 at 0:52










                          • I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
                            – Eric Hepperle - CodeSlayer2010
                            Jul 22 '16 at 20:54


















                          • External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
                            – fixer1234
                            Oct 10 '15 at 0:52










                          • I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
                            – Eric Hepperle - CodeSlayer2010
                            Jul 22 '16 at 20:54
















                          External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
                          – fixer1234
                          Oct 10 '15 at 0:52




                          External links can break, in which case this would be more of a hint than an answer. It would be better to include the essential information here and use the link just for attribution and further reading.
                          – fixer1234
                          Oct 10 '15 at 0:52












                          I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
                          – Eric Hepperle - CodeSlayer2010
                          Jul 22 '16 at 20:54




                          I know its old, but I want to make a comment for anyone thinking about clicking on that link -- DONT!!! This question is about 'GanttProject' but the link refers to a Microsoft product. Two different things.
                          – Eric Hepperle - CodeSlayer2010
                          Jul 22 '16 at 20:54










                          up vote
                          0
                          down vote













                          I have planned many projects where tasks were permitted to be worked on over weekends. It is just a matter of setting the correct working time for the resources assigned to the task. If the resource(s) assigned are permitted to work on Saturday and Sunday then any tasks to which they are assigned will automatically be scheduled on those days.



                          How you set the working time for resources differs depending on which version of Project you are using. It changed slightly from MS-P 2010 onwards.



                          In both versions you go to the Resource Sheet, select the resource you want to modify and double-click on their calendar (right hand side of sheet). A common source of confusion is that the calendar is named the same as the Project's calendar, but when selected from the Resource Sheet is specific and personal to that user alone.



                          Having opened the resource's calendar's Change Working Time dialog it now differs depending on verison. In 2010 onward you go to the Working Week tab and enter a new [default] entry, then select the "Details" button and ensure you have selected all days on which the user is working. Accept the changes and ensure the dates are correct for the period of time the resource is working the new hours. You can add as many rows describing non-standard hours as you want...



                          On prior versions of MS-P, if I can remember correctly, you need to select Sat and Sun in the column headers of the calendar box and then click the radio button indicating Working Days or Non-Standard Working Days (in which case you need to manually enter the hours they work on the selected days).



                          Typically I have normal working resources, set up the usual way, and then specific weekend-working resources who work weekend shifts to get stuff done, but do not work normal weekdays. So I create two (or more) different resources, one with weekday working and one with weekend working. When I assign a weekend-working-only resource to a task MS-P will only schedule it to be worked on over the weekend. But you could easily mix and match within a single resource...



                          These kinds of changes can be done at any time during a project- If you suddenly realise you need to get something done over a weekend, just apply a resource to it that can work over the weekend and the task will be scheduled over a weekend. Changed your mind? Just allocate a different (non-weekend working) resource and the task will be scheduled for the working week (you'll have to recalcuate/levle the plan obviously, it won't just happen automatically)






                          share|improve this answer



















                          • 1




                            It appears that the OP was not using MS Project, his question specifies GanttProject.
                            – dav
                            Jan 27 '14 at 17:37










                          • Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
                            – Marv Mills
                            Jan 29 '14 at 13:10















                          up vote
                          0
                          down vote













                          I have planned many projects where tasks were permitted to be worked on over weekends. It is just a matter of setting the correct working time for the resources assigned to the task. If the resource(s) assigned are permitted to work on Saturday and Sunday then any tasks to which they are assigned will automatically be scheduled on those days.



                          How you set the working time for resources differs depending on which version of Project you are using. It changed slightly from MS-P 2010 onwards.



                          In both versions you go to the Resource Sheet, select the resource you want to modify and double-click on their calendar (right hand side of sheet). A common source of confusion is that the calendar is named the same as the Project's calendar, but when selected from the Resource Sheet is specific and personal to that user alone.



                          Having opened the resource's calendar's Change Working Time dialog it now differs depending on verison. In 2010 onward you go to the Working Week tab and enter a new [default] entry, then select the "Details" button and ensure you have selected all days on which the user is working. Accept the changes and ensure the dates are correct for the period of time the resource is working the new hours. You can add as many rows describing non-standard hours as you want...



                          On prior versions of MS-P, if I can remember correctly, you need to select Sat and Sun in the column headers of the calendar box and then click the radio button indicating Working Days or Non-Standard Working Days (in which case you need to manually enter the hours they work on the selected days).



                          Typically I have normal working resources, set up the usual way, and then specific weekend-working resources who work weekend shifts to get stuff done, but do not work normal weekdays. So I create two (or more) different resources, one with weekday working and one with weekend working. When I assign a weekend-working-only resource to a task MS-P will only schedule it to be worked on over the weekend. But you could easily mix and match within a single resource...



                          These kinds of changes can be done at any time during a project- If you suddenly realise you need to get something done over a weekend, just apply a resource to it that can work over the weekend and the task will be scheduled over a weekend. Changed your mind? Just allocate a different (non-weekend working) resource and the task will be scheduled for the working week (you'll have to recalcuate/levle the plan obviously, it won't just happen automatically)






                          share|improve this answer



















                          • 1




                            It appears that the OP was not using MS Project, his question specifies GanttProject.
                            – dav
                            Jan 27 '14 at 17:37










                          • Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
                            – Marv Mills
                            Jan 29 '14 at 13:10













                          up vote
                          0
                          down vote










                          up vote
                          0
                          down vote









                          I have planned many projects where tasks were permitted to be worked on over weekends. It is just a matter of setting the correct working time for the resources assigned to the task. If the resource(s) assigned are permitted to work on Saturday and Sunday then any tasks to which they are assigned will automatically be scheduled on those days.



                          How you set the working time for resources differs depending on which version of Project you are using. It changed slightly from MS-P 2010 onwards.



                          In both versions you go to the Resource Sheet, select the resource you want to modify and double-click on their calendar (right hand side of sheet). A common source of confusion is that the calendar is named the same as the Project's calendar, but when selected from the Resource Sheet is specific and personal to that user alone.



                          Having opened the resource's calendar's Change Working Time dialog it now differs depending on verison. In 2010 onward you go to the Working Week tab and enter a new [default] entry, then select the "Details" button and ensure you have selected all days on which the user is working. Accept the changes and ensure the dates are correct for the period of time the resource is working the new hours. You can add as many rows describing non-standard hours as you want...



                          On prior versions of MS-P, if I can remember correctly, you need to select Sat and Sun in the column headers of the calendar box and then click the radio button indicating Working Days or Non-Standard Working Days (in which case you need to manually enter the hours they work on the selected days).



                          Typically I have normal working resources, set up the usual way, and then specific weekend-working resources who work weekend shifts to get stuff done, but do not work normal weekdays. So I create two (or more) different resources, one with weekday working and one with weekend working. When I assign a weekend-working-only resource to a task MS-P will only schedule it to be worked on over the weekend. But you could easily mix and match within a single resource...



                          These kinds of changes can be done at any time during a project- If you suddenly realise you need to get something done over a weekend, just apply a resource to it that can work over the weekend and the task will be scheduled over a weekend. Changed your mind? Just allocate a different (non-weekend working) resource and the task will be scheduled for the working week (you'll have to recalcuate/levle the plan obviously, it won't just happen automatically)






                          share|improve this answer














                          I have planned many projects where tasks were permitted to be worked on over weekends. It is just a matter of setting the correct working time for the resources assigned to the task. If the resource(s) assigned are permitted to work on Saturday and Sunday then any tasks to which they are assigned will automatically be scheduled on those days.



                          How you set the working time for resources differs depending on which version of Project you are using. It changed slightly from MS-P 2010 onwards.



                          In both versions you go to the Resource Sheet, select the resource you want to modify and double-click on their calendar (right hand side of sheet). A common source of confusion is that the calendar is named the same as the Project's calendar, but when selected from the Resource Sheet is specific and personal to that user alone.



                          Having opened the resource's calendar's Change Working Time dialog it now differs depending on verison. In 2010 onward you go to the Working Week tab and enter a new [default] entry, then select the "Details" button and ensure you have selected all days on which the user is working. Accept the changes and ensure the dates are correct for the period of time the resource is working the new hours. You can add as many rows describing non-standard hours as you want...



                          On prior versions of MS-P, if I can remember correctly, you need to select Sat and Sun in the column headers of the calendar box and then click the radio button indicating Working Days or Non-Standard Working Days (in which case you need to manually enter the hours they work on the selected days).



                          Typically I have normal working resources, set up the usual way, and then specific weekend-working resources who work weekend shifts to get stuff done, but do not work normal weekdays. So I create two (or more) different resources, one with weekday working and one with weekend working. When I assign a weekend-working-only resource to a task MS-P will only schedule it to be worked on over the weekend. But you could easily mix and match within a single resource...



                          These kinds of changes can be done at any time during a project- If you suddenly realise you need to get something done over a weekend, just apply a resource to it that can work over the weekend and the task will be scheduled over a weekend. Changed your mind? Just allocate a different (non-weekend working) resource and the task will be scheduled for the working week (you'll have to recalcuate/levle the plan obviously, it won't just happen automatically)







                          share|improve this answer














                          share|improve this answer



                          share|improve this answer








                          edited Nov 4 '13 at 13:42

























                          answered Aug 6 '13 at 12:43









                          Marv Mills

                          1816




                          1816








                          • 1




                            It appears that the OP was not using MS Project, his question specifies GanttProject.
                            – dav
                            Jan 27 '14 at 17:37










                          • Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
                            – Marv Mills
                            Jan 29 '14 at 13:10














                          • 1




                            It appears that the OP was not using MS Project, his question specifies GanttProject.
                            – dav
                            Jan 27 '14 at 17:37










                          • Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
                            – Marv Mills
                            Jan 29 '14 at 13:10








                          1




                          1




                          It appears that the OP was not using MS Project, his question specifies GanttProject.
                          – dav
                          Jan 27 '14 at 17:37




                          It appears that the OP was not using MS Project, his question specifies GanttProject.
                          – dav
                          Jan 27 '14 at 17:37












                          Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
                          – Marv Mills
                          Jan 29 '14 at 13:10




                          Doh! Missed that bit of vital info. That's 10 mins of my life I won't get back :)
                          – Marv Mills
                          Jan 29 '14 at 13:10










                          up vote
                          0
                          down vote













                          there is a solution. On Calender you can change the properties for the 24 hours calender. Then you enter the standard hour and select treat "sunday as standard" and treat "saturday as standard". You have to enter the working hours again but, each time you select it. Then I assigned to all ressources the 24hours calender and it worked fine for me.






                          share|improve this answer

























                            up vote
                            0
                            down vote













                            there is a solution. On Calender you can change the properties for the 24 hours calender. Then you enter the standard hour and select treat "sunday as standard" and treat "saturday as standard". You have to enter the working hours again but, each time you select it. Then I assigned to all ressources the 24hours calender and it worked fine for me.






                            share|improve this answer























                              up vote
                              0
                              down vote










                              up vote
                              0
                              down vote









                              there is a solution. On Calender you can change the properties for the 24 hours calender. Then you enter the standard hour and select treat "sunday as standard" and treat "saturday as standard". You have to enter the working hours again but, each time you select it. Then I assigned to all ressources the 24hours calender and it worked fine for me.






                              share|improve this answer












                              there is a solution. On Calender you can change the properties for the 24 hours calender. Then you enter the standard hour and select treat "sunday as standard" and treat "saturday as standard". You have to enter the working hours again but, each time you select it. Then I assigned to all ressources the 24hours calender and it worked fine for me.







                              share|improve this answer












                              share|improve this answer



                              share|improve this answer










                              answered Mar 6 '14 at 7:46









                              Max

                              1




                              1






















                                  up vote
                                  0
                                  down vote













                                  Project > Properties > Duration > change number of days in a month to 31 instead of the default 20.






                                  share|improve this answer

























                                    up vote
                                    0
                                    down vote













                                    Project > Properties > Duration > change number of days in a month to 31 instead of the default 20.






                                    share|improve this answer























                                      up vote
                                      0
                                      down vote










                                      up vote
                                      0
                                      down vote









                                      Project > Properties > Duration > change number of days in a month to 31 instead of the default 20.






                                      share|improve this answer












                                      Project > Properties > Duration > change number of days in a month to 31 instead of the default 20.







                                      share|improve this answer












                                      share|improve this answer



                                      share|improve this answer










                                      answered Nov 12 '15 at 11:31









                                      SmallQ

                                      91




                                      91






















                                          up vote
                                          0
                                          down vote













                                          how to add an occasional weekend to be a working weekend?



                                          You can go to Project->Properties->Calendar
                                          go to One-off tab
                                          click on Add
                                          put in the target saturday or sunday

                                          Change the type from "holiday" to "working" day
                                          then
                                          Continue to charge forward in life with a smile






                                          share|improve this answer

























                                            up vote
                                            0
                                            down vote













                                            how to add an occasional weekend to be a working weekend?



                                            You can go to Project->Properties->Calendar
                                            go to One-off tab
                                            click on Add
                                            put in the target saturday or sunday

                                            Change the type from "holiday" to "working" day
                                            then
                                            Continue to charge forward in life with a smile






                                            share|improve this answer























                                              up vote
                                              0
                                              down vote










                                              up vote
                                              0
                                              down vote









                                              how to add an occasional weekend to be a working weekend?



                                              You can go to Project->Properties->Calendar
                                              go to One-off tab
                                              click on Add
                                              put in the target saturday or sunday

                                              Change the type from "holiday" to "working" day
                                              then
                                              Continue to charge forward in life with a smile






                                              share|improve this answer












                                              how to add an occasional weekend to be a working weekend?



                                              You can go to Project->Properties->Calendar
                                              go to One-off tab
                                              click on Add
                                              put in the target saturday or sunday

                                              Change the type from "holiday" to "working" day
                                              then
                                              Continue to charge forward in life with a smile







                                              share|improve this answer












                                              share|improve this answer



                                              share|improve this answer










                                              answered Aug 22 at 18:15









                                              Marklar

                                              1




                                              1






























                                                  draft saved

                                                  draft discarded




















































                                                  Thanks for contributing an answer to Super User!


                                                  • Please be sure to answer the question. Provide details and share your research!

                                                  But avoid



                                                  • Asking for help, clarification, or responding to other answers.

                                                  • Making statements based on opinion; back them up with references or personal experience.


                                                  To learn more, see our tips on writing great answers.





                                                  Some of your past answers have not been well-received, and you're in danger of being blocked from answering.


                                                  Please pay close attention to the following guidance:


                                                  • Please be sure to answer the question. Provide details and share your research!

                                                  But avoid



                                                  • Asking for help, clarification, or responding to other answers.

                                                  • Making statements based on opinion; back them up with references or personal experience.


                                                  To learn more, see our tips on writing great answers.




                                                  draft saved


                                                  draft discarded














                                                  StackExchange.ready(
                                                  function () {
                                                  StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fsuperuser.com%2fquestions%2f601713%2fhow-to-allow-enable-the-weekends-as-working-period-in-gantt-project%23new-answer', 'question_page');
                                                  }
                                                  );

                                                  Post as a guest















                                                  Required, but never shown





















































                                                  Required, but never shown














                                                  Required, but never shown












                                                  Required, but never shown







                                                  Required, but never shown

































                                                  Required, but never shown














                                                  Required, but never shown












                                                  Required, but never shown







                                                  Required, but never shown







                                                  Popular posts from this blog

                                                  AnyDesk - Fatal Program Failure

                                                  How to calibrate 16:9 built-in touch-screen to a 4:3 resolution?

                                                  QoS: MAC-Priority for clients behind a repeater