How many activities per week should I be doing with my scrum team?











up vote
4
down vote

favorite












As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?










share|improve this question






















  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    Nov 17 at 9:26










  • Agile. Taking the team to the next level.
    – user32613
    Nov 17 at 9:26















up vote
4
down vote

favorite












As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?










share|improve this question






















  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    Nov 17 at 9:26










  • Agile. Taking the team to the next level.
    – user32613
    Nov 17 at 9:26













up vote
4
down vote

favorite









up vote
4
down vote

favorite











As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?










share|improve this question













As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?







scrum agile scrum-master






share|improve this question













share|improve this question











share|improve this question




share|improve this question










asked Nov 17 at 8:04









user32613

41111




41111












  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    Nov 17 at 9:26










  • Agile. Taking the team to the next level.
    – user32613
    Nov 17 at 9:26


















  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    Nov 17 at 9:26










  • Agile. Taking the team to the next level.
    – user32613
    Nov 17 at 9:26
















what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
Nov 17 at 9:26




what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
Nov 17 at 9:26












Agile. Taking the team to the next level.
– user32613
Nov 17 at 9:26




Agile. Taking the team to the next level.
– user32613
Nov 17 at 9:26










3 Answers
3






active

oldest

votes

















up vote
6
down vote



accepted










You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






share|improve this answer




























    up vote
    4
    down vote













    How many activities should you organise?



    None.



    How many activities should you facilitate if requested by the team?



    As many as they want.






    share|improve this answer





















    • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
      – user32613
      Nov 17 at 20:38






    • 2




      With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
      – Barnaby Golden
      Nov 17 at 22:37




















    up vote
    1
    down vote













    There is no particular number associated with this, but I think it should be totally based on outcomes of your daily Scrum meeting (daily standup) which is must.



    In Scrum meeting if you find something which is blocking deliverables then to overcome those you may need to align more sessions/meeting.






    share|improve this answer





















    • How would a workshop about the Agile process help with blockers in their daily work?
      – nvoigt
      Nov 20 at 16:26










    • My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
      – PrashantG
      Nov 20 at 18:13











    Your Answer








    StackExchange.ready(function() {
    var channelOptions = {
    tags: "".split(" "),
    id: "208"
    };
    initTagRenderer("".split(" "), "".split(" "), channelOptions);

    StackExchange.using("externalEditor", function() {
    // Have to fire editor after snippets, if snippets enabled
    if (StackExchange.settings.snippets.snippetsEnabled) {
    StackExchange.using("snippets", function() {
    createEditor();
    });
    }
    else {
    createEditor();
    }
    });

    function createEditor() {
    StackExchange.prepareEditor({
    heartbeatType: 'answer',
    convertImagesToLinks: false,
    noModals: true,
    showLowRepImageUploadWarning: true,
    reputationToPostImages: null,
    bindNavPrevention: true,
    postfix: "",
    imageUploader: {
    brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
    contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
    allowUrls: true
    },
    noCode: true, onDemand: true,
    discardSelector: ".discard-answer"
    ,immediatelyShowMarkdownHelp:true
    });


    }
    });














    draft saved

    draft discarded


















    StackExchange.ready(
    function () {
    StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25260%2fhow-many-activities-per-week-should-i-be-doing-with-my-scrum-team%23new-answer', 'question_page');
    }
    );

    Post as a guest















    Required, but never shown

























    3 Answers
    3






    active

    oldest

    votes








    3 Answers
    3






    active

    oldest

    votes









    active

    oldest

    votes






    active

    oldest

    votes








    up vote
    6
    down vote



    accepted










    You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



    I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



    In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






    share|improve this answer

























      up vote
      6
      down vote



      accepted










      You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



      I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



      In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






      share|improve this answer























        up vote
        6
        down vote



        accepted







        up vote
        6
        down vote



        accepted






        You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



        I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



        In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






        share|improve this answer












        You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



        I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



        In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.







        share|improve this answer












        share|improve this answer



        share|improve this answer










        answered Nov 17 at 9:47









        nvoigt

        3,084715




        3,084715






















            up vote
            4
            down vote













            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.






            share|improve this answer





















            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              Nov 17 at 20:38






            • 2




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              Nov 17 at 22:37

















            up vote
            4
            down vote













            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.






            share|improve this answer





















            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              Nov 17 at 20:38






            • 2




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              Nov 17 at 22:37















            up vote
            4
            down vote










            up vote
            4
            down vote









            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.






            share|improve this answer












            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.







            share|improve this answer












            share|improve this answer



            share|improve this answer










            answered Nov 17 at 20:21









            Barnaby Golden

            8,2951721




            8,2951721












            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              Nov 17 at 20:38






            • 2




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              Nov 17 at 22:37




















            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              Nov 17 at 20:38






            • 2




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              Nov 17 at 22:37


















            Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
            – user32613
            Nov 17 at 20:38




            Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
            – user32613
            Nov 17 at 20:38




            2




            2




            With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
            – Barnaby Golden
            Nov 17 at 22:37






            With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
            – Barnaby Golden
            Nov 17 at 22:37












            up vote
            1
            down vote













            There is no particular number associated with this, but I think it should be totally based on outcomes of your daily Scrum meeting (daily standup) which is must.



            In Scrum meeting if you find something which is blocking deliverables then to overcome those you may need to align more sessions/meeting.






            share|improve this answer





















            • How would a workshop about the Agile process help with blockers in their daily work?
              – nvoigt
              Nov 20 at 16:26










            • My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
              – PrashantG
              Nov 20 at 18:13















            up vote
            1
            down vote













            There is no particular number associated with this, but I think it should be totally based on outcomes of your daily Scrum meeting (daily standup) which is must.



            In Scrum meeting if you find something which is blocking deliverables then to overcome those you may need to align more sessions/meeting.






            share|improve this answer





















            • How would a workshop about the Agile process help with blockers in their daily work?
              – nvoigt
              Nov 20 at 16:26










            • My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
              – PrashantG
              Nov 20 at 18:13













            up vote
            1
            down vote










            up vote
            1
            down vote









            There is no particular number associated with this, but I think it should be totally based on outcomes of your daily Scrum meeting (daily standup) which is must.



            In Scrum meeting if you find something which is blocking deliverables then to overcome those you may need to align more sessions/meeting.






            share|improve this answer












            There is no particular number associated with this, but I think it should be totally based on outcomes of your daily Scrum meeting (daily standup) which is must.



            In Scrum meeting if you find something which is blocking deliverables then to overcome those you may need to align more sessions/meeting.







            share|improve this answer












            share|improve this answer



            share|improve this answer










            answered Nov 20 at 15:52









            PrashantG

            563




            563












            • How would a workshop about the Agile process help with blockers in their daily work?
              – nvoigt
              Nov 20 at 16:26










            • My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
              – PrashantG
              Nov 20 at 18:13


















            • How would a workshop about the Agile process help with blockers in their daily work?
              – nvoigt
              Nov 20 at 16:26










            • My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
              – PrashantG
              Nov 20 at 18:13
















            How would a workshop about the Agile process help with blockers in their daily work?
            – nvoigt
            Nov 20 at 16:26




            How would a workshop about the Agile process help with blockers in their daily work?
            – nvoigt
            Nov 20 at 16:26












            My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
            – PrashantG
            Nov 20 at 18:13




            My bad, I thought workshop is about the ceremonies and not about the agile process. If its more about educating team on Agile process then I think it should be periodically as and when you spotted the improvements
            – PrashantG
            Nov 20 at 18:13


















            draft saved

            draft discarded




















































            Thanks for contributing an answer to Project Management Stack Exchange!


            • Please be sure to answer the question. Provide details and share your research!

            But avoid



            • Asking for help, clarification, or responding to other answers.

            • Making statements based on opinion; back them up with references or personal experience.


            To learn more, see our tips on writing great answers.





            Some of your past answers have not been well-received, and you're in danger of being blocked from answering.


            Please pay close attention to the following guidance:


            • Please be sure to answer the question. Provide details and share your research!

            But avoid



            • Asking for help, clarification, or responding to other answers.

            • Making statements based on opinion; back them up with references or personal experience.


            To learn more, see our tips on writing great answers.




            draft saved


            draft discarded














            StackExchange.ready(
            function () {
            StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25260%2fhow-many-activities-per-week-should-i-be-doing-with-my-scrum-team%23new-answer', 'question_page');
            }
            );

            Post as a guest















            Required, but never shown





















































            Required, but never shown














            Required, but never shown












            Required, but never shown







            Required, but never shown

































            Required, but never shown














            Required, but never shown












            Required, but never shown







            Required, but never shown







            Popular posts from this blog

            QoS: MAC-Priority for clients behind a repeater

            Ивакино (Тотемский район)

            Can't locate Autom4te/ChannelDefs.pm in @INC (when it definitely is there)